Project information:

Architect: Renker-Eich-Parks

Contractor: Charles Perry Partners, Inc. (CPPI)

PCSB Project Manager: Bruce Stott

Project Budget: $5.9 Million

Start Date: December 2018

Completion: October 2019

 

Construction/Renovation of:

  • Removal of temporary classrooms that are currently on site
  • Construction of a new 12 classroom wing
  • Upgrade intrusion system campus wide
  • Redesign of the existing bus loop and walkway canopies to accommodate the new classroom building
  • New fire line and connection to the right-of-way in front of campus

Work Progress:

  • Final Inspection of Punch List/Warranty Items scheduled for 7/27/20
  • Project is complete
2017.01.20
2017.01.20
2017.01.20
2019.05.24
2019.05.24
2019.05.24
2019.05.24
2019.05.24
2019.05.24
2019.05.24
2019.05.24
2019.05.24
2019.07.11 DJI_0052
2019.09.03  4
2019.09.03 1 5
2019.09.03 1 6
2019.09.09 1 7
2019.09.03 1 8
2019.09.03 1 1
2019.09.03 1 3
2019.09.03 1 2