Skip To Main Content

2021 Richard O. Jacobson Technical High School at Seminole

Richard O. Jacobson Technical High School - Veterinary Science Building

  • Updated 1/12/21

    Project information:

    Architect: Ranon & Partners, Inc.

    Contractor: Je Dunn Construction

    PCSB Project Manager: Rich Gauvey

    Project Budget: $4.6 million

    Start Date:  April 2020

    Completion: January 2021

     

    Construction/Renovation of:

    New pre-Engineered metal veterinary science building

    Project status:

    ·    Building is complete, waiting on final power form utility company to substantially complete building.

     

     

     

     

     

20.24.07 -Sheathing complete on South and West
20.24.07 -Barn Roof
20.24.07 -Ductworkt
20.24.07 - Mechanical Housekeeping Pad
20.24.07 - Topout of walls
20.08.03 Exterior waterproofing
20.08.03 Exterior  framing at barn
20.08.03 Fire sprinkler
20.08.03 Sheating at the clerestories
20.08.03 Bathroom plumbing rough-in
20.08.03 Ductwork install
20.07.08 Pulling wire at transformer
20.07.08 West wall soffit framing
20.07.08 Sheathing install at the Barn
20.07.08 Insulation install
20.07.08 Interior Framing at the Barn
20.07.08 Condensing Unit installed