San Jose Elementary-Campus Renovations
Updated on 1/7/22
Project information:
Architect: Wilder Architects, Inc.
Contractor: A.D. Morgan Corporation
CM Project Website: www.sanjoseelementary.com
PCSB Project Coordinator: Cliff Powers
Project Budget: $3.3 Millions
Start Date: December 2020
Completion: July 2021
Construction/Renovation of
Exterior:
Put Marque Sign at the road entrance near Lady of Lourdes
Clear any overgrowth from the front and sides of the school
Relocate the dumpsters and new enclosure to where the bike racks currently are
Create a main entrance presence
Look at possibility of a new bus drive or a renovated parking lot
Look at bike rack area, remove all concrete and make a green space
Media Center:
New ceilings, lights and paint
Administration Building:
Add a conference room
Cafeteria:
Hide all air condensers and air conditioners, rework all a/c in cafeteria
New flooring
New ceilings and lights
Replace the hood in the kitchen – upgrade the electrical
Replace serving line
Project status:
Project is substantially complete and currenlty in punch out.