2021 Sanderlin IB K-8 School

Sanderlin IB K-8 10 New room addition

Updated on 8/23/21

Project information

Architect: Williamson Dacar Associates, Inc.

Contractor: Skanska USA Building, Inc.

CM Project Website: https://sites.google.com/view/sanderlinpk-8-prototype

PCSB Project Coordinator: Brian Long

Project Budget:  $5.9 Million

Start Date:  November 2020

Completion: July 2021

 

Construction/Renovation of: 

New 10 room Building


Project status:

Project is substantially complete and currenlty in punch out.

 



21-2-8-aPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-2-8-BPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-2-8-CPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-2-8-DPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-2-22--PCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-2-22PCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-2-22-PCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-2-22---PCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-3-9 cPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-3-9 bPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-3-9 aPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-3-9 PCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-4-5cPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-4-5bPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-4-5aPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-4-5PCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-6-21PCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-6-21aPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-6-21cPCS-Sanderlin IB PK-8-Weekly Dashboard w.e
21-6-21bPCS-Sanderlin IB PK-8-Weekly Dashboard w.e