Project information

Architect: Williamson Dacar Associates, Inc.

Contractor: Ajax Building Corporation

CM Project Website: https://www.ajaxbuilding.com/projects/pinellas-county-schools-shore-acres-elementary-classroom-addition/

PCSB Project Coordinator: Rich Gauvey

Project Budget: $3.8 Million

Start Date: November 2020

Completion: July 2021

 

Construction/Renovation of:

New 6 classroom building


Project status:

Project is subtantially completed and currently working on punch list.