2022 Coachman Service Center

Coachman Service Center - New service garage

Coachman Service Center - New service garage

Updated on 12/13/22

Project information:

Architect: Sweet Sparkman Architecture

Contractor: Creative Contractors, Inc.

CM Project Website: https://coachmanservicecenter.shutterfly.com/

PCSB Project Coordinator: Bruce Stott

Project Budget: $6.5 Million

Start Date: December 2021

Completion: April 2023

 

Construction/Renovation of:

The project includes a new bus service garage to hold and maintain the buses servicing our mid county schools.   The project’s goal is to construct a new bus service garage with associated work spaces to be located at the south-east of the property, a remodel of the existing facilities kitchen area to turn it from the transportation command center back into a kitchen to serve the school.   There will also be site work associated with the project to include a revised parking lot layout and drive access.

Demolition will include:

  • Demolition of Building 1

 

New Construction will include:

  • New bus service garage to include:
    • 5 bay service garage: 5,475 Sq.Ft
    • Flammable storage: 450 Sq.Ft.
    • Tool Room: 900 Sq.Ft.
    • Garage Foreman/Clerk/Lead Mechanic: 500 Sq.Ft.
    • Parts Room/Parts Office : 1,700 Sq.Ft.
    • 5 Offices: 750 Sq.Ft.
    • Bus Service Recorder: 250 Sq.Ft.
    • Restrooms: 900 Sq.Ft.
    • Lounge: 1,000 Sq.Ft
    • Mechanical/Electrical/Comm.: 850 Sq.Ft
    • Clerical/Storage/Vault: 600 Sq.Ft

Total:                                                                                             13,375 Sq.Ft.

  • New Transportation Command Center: 2,400 Sq.Ft.

 

Renovations and remodel to include:

  • Converting the existing Transportation Command Center back into a working kitchen
  • Remodel existing school auditorium (ceilings, lights, flooring, paint)

 

Site Work:

  • Create new parking lot layout and entry drive for the buses and staff parking
  • Add additional propane fueling stations for buses.

Project status:

 

  • Completed Last Week: 
  • Completed installation of new signage at transportation offices in Building #2. 
  • Continued final grading and asphalt for southwest end of site. 
  • Completed installation of new asphalt south of existing Building #2 and Building #3. 
  • Continued footers and sidewalk for covered walkway. 
  • Continued hanging light fixtures in new service building. 
  • Continued rough in of mechanical controls and low voltage electrical for new service building. 
  • Began electrical and mechanical trim on interior of new service building. 
  • Continued removal of excess spoils from site. 
  • Completed priming and painting of stair railing. Continued touch up paint on interior of service building. 
  • Completed installation of safety gate at mezzanine. 
  • Began installation of lockers in Restrooms #104 & #106.

 

  • Scheduled This Week:
  •  Continue final grading and asphalt for southwest end of site.
  •  Continue footers and sidewalk for covered walkway.
  •  Continue rough in of mechanical controls and low voltage electrical for new service building. .
  •  Continue hanging light fixtures in new service building.
  •  Complete installation of condenser units on south exterior of new service building.
  •  Complete priming and painting of ship ladder to roof hatch.

Rendering3
Rendering2
Picture1Rendering
Rendering4
Coachman survey 1-26-5
Coachman survey 1-26-12
Coachman survey 1-26-15
Coachman survey 1-26-1
2022-04-18 308 Weekly Update
2022-04-18a 9308 Weekly Update
2022-06-13
Coachman Aerial Survey Photos 11 29-8
Coachman Aerial Survey Photos 11 29-14
Coachman Aerial Survey Photos 11 29-7
Coachman Aerial Survey Photos 11 29-13
Coachman Aerial Survey Photos 11 29-11
Coachman Aerial Survey Photos 11 29-6
Coachman Aerial Survey Photos 11 29-10