2022 St. Petersburg High School

2021 St. Petersburg High - Major Renovations Campus Wide

Updated 11/9/21

Project information:

Architect: Rowe Architects, Inc.

Contractor: Creative Contractors, Inc.

PCSB Project Manager: Rich Gauvey

Project Budget: $33 Million

Start Date: June 2019

Completion: August 2021

 

Construction/Renovation of:

  • Major renovations campus wide to create cafeteria, art room and band room. 
  • Demolish Existing Buildings 2, 3, and 8.
  • Create a new covered entrance from the west visitor’s parking lot to the front entrance of the school parallel to 5th Ave. 
  • Create a new courtyard where buildings 2 and 3 were demolished.
  • New ticket booth/concession stand/restroom building to be an estimated 1,500 square feet

Renovations to include:

  • Stucco Repairs as needed throughout campus
  • Painting (interior & exterior) Enhance the trim of Building 1 to a different color than the base color of the walls
  • Tuck-pointing As needed
  • Roof replacement:  Building 1 all modified roofs to be replaced.
    • Building 4 replace modified roof to the deck and replace the tile roof.
    • Building 5 replace the tile roof
  • Line domestic water lines in Building 1
  • Replacement of exhaust fans in Building 5
  • Replace Trane water cooled Chiller
  • Replace 2 fresh air handling units in Building 5
  • Replace rooftop air handler in Building 1.
  • Provide strip heaters for Buildings 1 & 4
  • Replacement of existing air handler units with new vertical fan coil units in Building 1 & 4
  • Replace chiller serving Buildings 1 & 4 and associated pumps and cooling tower
  • New ceilings and lights in Buildings 1 & 4
  • New low voltage/technology infrastructure  (access control, network, phones, intrusion and cameras) throughout campus
  • New fire alarm system throughout campus
  • Install new Fire sprinkler and fire pump throughout campus
  • Repair all termite damage throughout Building 1
  • Repair fire barriers in attic of Building 1.
  • Securing school entrance:
    • Renovate existing administration office suite to enclose existing open entrance vestibule and create a visitors waiting area and secured sign in area.
  • Replace counter tops and sinks in Building 4 restrooms
  • Auditorium:
    • Enhance the trim to a different color than the base color of the walls
    • Replace carpeting and stain floor under seats
    • Provide ADA seating
    • Replace rear entry doors to the seating area
  • Small auditorium in Building 1: replace flooring, lights, and enhance the trim to a different color than the base color of the walls.
  • Building 1 Carpet
  • Site work
  • Building 1 hallways:
    • Replace metal screening with windows, remove abandoned conduits, and restore painted brick base to original brick color.

Project status:

Week of 11/9/21

Working on exterior east elevation of Builing 4 envelope.

Sidewalks on the east side of courtyard adjucent to Building 4.

Courtyard landscape/hardscape

Project substantial completion is set for December 4. 2021.

St. Petersburg High ROWE ARCHITECTS 58R front entry side by side
St. Petersburg High B02 Colonnade Perspective 1
St. Petersburg High B02 Colonnade Perspective 2
St. Petersburg High B02 Courtyard Perspective 2
St. Petersburg High B02 Dining Perspective
St. Petersburg High B02 Home Ec Perspective
St. Petersburg High Construction 2019.06.25 3
St. Petersburg High Construction 2019.06.25 4
St. Petersburg High Construction 2019.06.25 5
St. Petersburg High Construction 2019.06.25 6
St. Petersburg High Construction 2019.06.25 1
St. Petersburg High Construction 2019.06.25 2
St. Petersburg High Construction Second FL core drills
St. Petersburg High Construction Third FL chilled water line
St. Petersburg High Construction Third Floor attic Chilled water line
St. Petersburg High Construction
St. Petersburg High Construction Ductwork
St. Petersburg High Construction Ductwork
2020.07.07 Camera
2020.07.07 CHW-HVAC
2020.07.07 Roof 1
2020.07.07 Courtyard
2020.07.07 Auditorium
2020.07.07 Elevator Pit
2020.07.07 Ceilings
2020.07.07 Corridor
2020.07.07 Ductwork
2020.07.07 Roof
2021-02-09b 9188 Progress Report - Jan 21
2021-02-09-a9188 Progress Report - Jan 21
2021-02-09 ---9188 Progress Report - Jan 21
2021-02-09- 9188 Progress Report - Jan 21
2021-02-09 --9188 Progress Report - Jan 21
2021-02-09 e9188 Progress Report - Jan 21
2021-02-09 9188 Progress Report - Jan 21
2021-02-09e 9188 Progress Report - Jan 21
2021-02-09d 9188 Progress Report - Jan 21
2021-02-09c 9188 Progress Report - Jan 21
2021-02-26 RPT_210226_SPHS_Weekly Snapshot
2021-02-26-RPT_210226_SPHS_Weekly Snapshot
2021-02-26--RPT_210226_SPHS_Weekly Snapshot
2021-02-26---RPT_210226_SPHS_Weekly Snapshot
2021-03-12 RPT_210312_SPHS_Weekly Snapshot
2021-03-12ARPT_210312_SPHS_Weekly Snapshot
2021-03-22DSPHS Progress Report - Feb 2021
2021-03-22CSPHS Progress Report - Feb 2021
2021-03-22BSPHS Progress Report - Feb 2021
2021-03-22ASPHS Progress Report - Feb 2021
2021-03-22GSPHS Progress Report - Feb 2021
2021-03-22FSPHS Progress Report - Feb 2021
2021-03-22ESPHS Progress Report - Feb 2021
2021-4-7bSPHS Progress Report - Mar 2021
2021-4-7dSPHS Progress Report - Mar 2021
2021-4-7cSPHS Progress Report - Mar 2021
2021-4-7eSPHS Progress Report - Mar 2021
2021-4-7fSPHS Progress Report - Mar 2021
2021-4-7gSPHS Progress Report - Mar 2021
2021-4-7hSPHS Progress Report - Mar 2021
2021-4-7SPHS Progress Report - Mar 2021
2021-4-7aSPHS Progress Report - Mar 2021
2021-5-21c
2021-5-21b
2021-5-21a
2021-06-07 a188 weekly report
2021-06-07   9188 weekly report
2021-06-07 b9188 weekly report