• San Jose Elementary-Campus Renovations

    Updated on 1/7/22

    Project information:

    Architect: Wilder Architects, Inc.

    Contractor: A.D. Morgan Corporation

    CM Project Website: www.sanjoseelementary.com

    PCSB Project Coordinator: Cliff Powers

    Project Budget: $3.3 Millions

    Start Date: December 2020

    Completion: July 2021

     

     

    Construction/Renovation of

    Exterior:

                    Put Marque Sign at the road entrance near Lady of Lourdes

                    Clear any overgrowth from the front and sides of the school

    Relocate the dumpsters and new enclosure to where the bike racks currently are

    Create a main entrance presence

    Look at possibility of a new bus drive or a renovated parking lot

    Look at bike rack area, remove all concrete and make a green space

    Media Center:

                    New ceilings, lights and paint

    Administration Building:

                    Add a conference room

    Cafeteria:

                    Hide all air condensers and air conditioners, rework all a/c in cafeteria

                    New flooring

                    New ceilings and lights

                    Replace the hood in the kitchen – upgrade the electrical

                    Replace serving line


    Project status:

    Project is substantially complete and currenlty in punch out.