• Gulf Beaches Elementary School - Replacement of 6 Portables

     

    Project Information:

    Architect: Spiezle Architectural Group

    Contractor: Creative Contractors, Inc.

    PCS Project Coordinator: Brian Long

    Project Budget: $3,100,000

    Start Date: April 2024

    Completion: August 2024

     

    Construction:

    This project is for the new construction of a six-classroom pocket village at Gulf Beaches Elementary School.  The goals of this project are to remove portable classrooms and create a six-classroom pocket village which will provide a learning community for the students and staff.

     

    Project Status:

    Week of 8/2/24

    • Substantial completion was completed 7/29/24 and punch lists are in progress
    • Certificate of Occupancy issued 8/1/24